Three stormwater teams fight over the only shared GIS specialist's calendar every iteration. What source of conflict should the Scrum Master / Team Coach name?
Select an answer to reveal the explanation.
Short Explanation
One plow and three snow routes is not a bad plow operator—it is a fleet-design problem. One GIS specialist and three stormwater boards will collide on the calendar. Name the scarce-resource structure, not the person's attitude.
Full Explanation
Structural and resource sources include scarce shared specialists split across teams. Fighting over the only GIS calendar is a team-design and capacity problem, not rainfall-sensor trivia or a character flaw. The Scrum Master / Team Coach makes that structure visible so the ART can change staffing, sequencing, or policies. Removing GIS from the municipal ART does not name the real source.