Teams on the new public works work-order ART are sent into the first PI Planning with no SAFe role or event training. What create-ART preparation should the RTE require?
Select an answer to reveal the explanation.
Short Explanation
Throwing public-works teams into PI Planning with no training is like handing out survey gear with no map. Teach the roles and the event first—then the room can plan work orders instead of guessing the ceremony. Cold-start PI Planning mostly produces confusion with sticky notes.
Full Explanation
ART launch steps include training teams and key roles before the first PI Planning. Without a shared language for PI Objectives, dependencies, and ROAM, the event cannot do its job. Calendar pressure, executive-only training, and tool demos are not substitutes. The RTE should sequence training, then launch, so the work-order ART’s first PI Planning is a planning event rather than an orientation.