Leaders staff the county elections systems ART with a random mix of teams that do not share a value stream or mission. What create-ART correction should the RTE recommend?
Select an answer to reveal the explanation.
Short Explanation
Random teams with an “elections ART” sticker still do not share a track. Design the train around one coherent value stream—ballots, voter systems, results—so the teams actually need each other. Extra meetings will not glue a grab-bag of teams into a mission.
Full Explanation
ART design requires a coherent value stream or shared mission so teams can plan, demo, and release together. When leaders staff the county elections systems ART with a random mix of teams that do not share a value stream or mission, the RTE should recommend redesigning the ART around a coherent value stream and shared mission rather than a random team mix. Extra meetings will not glue a grab-bag of teams into an elections mission such as ballots, voter systems, or results. Keeping the random mix and relying on extra Scrum of Scrums to invent a mission later treats coordination theater as design. Splitting every team into single-function component groups so specialization is clearer often increases handoffs and moves further from a value-stream ART. Delaying all role identification until after three PIs of the random design postpones other create-ART steps while leaving the core topology wrong. Exam caveat: redesign may be incremental, but the target remains a coherent mission and value stream—not permanent collage with more syncs. Operational check: facilitate a short redesign session that restates the elections operational value stream, groups teams that share that mission, and adjusts ART membership and board scope before the next PI Planning.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.