A sawmill safety PLC that guards the head saw has a firmware flaw. The vendor procedure needs a tested outage and a signed image. A forum file is proposed for tonight while the line is cutting. Which remediation fits?
Select an answer to reveal the explanation.
Short Explanation
You do not pour an unlabeled bottle into a safety system because a forum said the mixture works. The sawmill safety PLC keeps its running image until the vendor signed procedure fits a planned outage. Loading a stranger's file while the head saw is cutting trades a known process for a guess.
Full Explanation
Remediation of a safety controller follows the vendor procedure and a window the process can survive. The flaw is real, the signed image and a tested outage are the method the vendor requires, and the line is cutting tonight. The fit is to leave the running safety image in place and take that signed image in the planned outage, with the forum file left unused. An unsigned file from a forum is not the vendor image, and a mid-cut reboot of the head-saw safety PLC adds a process hazard the procedure was written to avoid. Swapping the safety PLC for a basic process controller that merely lacks this flaw listing destroys the independent safety function. The absence of a matching bulletin is not a safety design. Ignoring the flaw because safety controllers are imagined to sit outside the threat model leaves a known weakness with no plan. Safety controllers are in the model, and they are patched by the vendor method rather than by a shrug. Exam caveat: a controller that is already failing safe is a different situation from a line that is still cutting on its current image. This stem is the second case, so the forum file is not a shortcut. Operational check: record the current safety image, schedule the vendor procedure against a mill outage, and confirm the forum file is not staged on the engineering station that can reach the safety PLC.