Two data centers are joined by one point-to-point Layer 2 circuit that is down, while the IP core and the fabric overlays stay healthy. The provider provisions this Ethernet service using a pseudowire. Which encapsulation is actually in the failed path?
Select an answer to reveal the explanation.
Short Explanation
When the footbridge is out, you do not blame the city map or a policy binder you are not using. You trace this outage to the pseudowire that emulates the point-to-point circuit. An EVPN VXLAN fabric overlay, EVPN over a segment-routed core, and an ACI policy fault are other encapsulations.
Full Explanation
This service uses a point-to-point pseudowire. That is the Layer 2 circuit that is down between these data centers. EVPN with VXLAN is the overlay that extends Layer 2 or Layer 3 across a data-center fabric, and those overlays are still healthy. EVPN over segment routing or MPLS carries that control plane across a segment-routed core. An ACI fault is policy or forwarding inside an ACI fabric, which is not this failed circuit. The pseudowire that emulates the point-to-point Layer 2 circuit that is down is the design that meets this requirement. EVPN with VXLAN, the overlay that extends segments across a data-center fabric is the wrong fit because that overlay extends segments across a data-center fabric, and the healthy fabric overlays are not the failed circuit. EVPN carried across a segment-routed MPLS core that is not this failed circuit is the wrong fit because that control plane rides a segment-routed core, and the failed service is a point-to-point circuit with the core still up. An ACI policy or forwarding fault inside a policy fabric that is not this circuit is the wrong fit because an ACI fault is a policy or forwarding problem inside an ACI fabric, and this circuit is a point-to-point emulation. Exam caveat: Match the encapsulation that is actually down. EVPN, segment routing, and ACI are real interconnect tools, and they are the wrong fault when the failed service is a pseudowire. Operational check: On the two data-center edges, confirm the point-to-point pseudowire is the circuit that is down and that the IP core and the overlays still forward.