During a standup on a stormwater-sensor project, a lead begins presenting a long earned-value slide deck. What format discipline should the team apply?
Select an answer to reveal the explanation.
Short Explanation
Standup format is simple: yesterday, today, blockers—not a TED Talk on earned value. Park the slide deck for a status or steering session. Keep the huddle short and disciplined.
Full Explanation
During a standup on a stormwater-sensor project, presenting a long earned-value slide deck breaks format discipline. Standups should stay on concise yesterday/today/blockers updates so the field and analytics team can coordinate quickly. EVM deep-dives belong in scheduled performance reviews where baselines, variances, and forecasts can be examined properly.
Requiring every standup to include a full EVM lecture guarantees chronic overtime meetings and dilutes impediment focus. Banning any mention of blockers to “stay positive” removes the standup’s main operational value. Extending every standup until the complete capital portfolio is reviewed turns a team sync into an enterprise portfolio committee.
Exam caveat: CAPM associates must distinguish agile/team coordination rituals from predictive performance-reporting forums. Both can exist on hybrid civic programs, but not as the same daily meeting.
Operational check: stop the slide deck, finish a short blocker-focused standup, and schedule a separate EVM status review with the audience that needs variance analysis against the stormwater baseline. Separating the forums also clarifies audiences: the field team needs blockers cleared; finance and sponsors need variance narratives. One bloated standup serves neither group well on stormwater programs.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.