A risk response plan for a civic garage states: expedite an alternate supplier if steel lead time exceeds 8 weeks. Lead time reaches 10 weeks. What should the team do?
Select an answer to reveal the explanation.
Short Explanation
Ten weeks is past the eight-week tripwire—time to run the play you already wrote. Expedite the alternate supplier instead of admiring the risk register. Planned responses earn their keep when triggers fire.
Full Explanation
Planned risk responses are meant to be executed when identified triggers occur. Here, exceeding the 8-week lead-time threshold should activate the alternate-supplier response. CAPM fundamentals stress following the risk strategy rather than treating registers as static paperwork.