For a pier rebuild, the risk register includes a threat of weather delay and an opportunity for an early material discount. What does that combination demonstrate?
Select an answer to reveal the explanation.
Short Explanation
Risk is not only 'bad stuff.' The register can hold storm delays and a chance to snag steel cheaper if you order early—both deserve an owner and a plan.
Full Explanation
Project risk includes uncertain events that can help or hurt objectives. A well-used risk register therefore holds threats and opportunities, along with analysis attributes and response approaches. Recording an early-purchase discount opportunity beside a delay threat is appropriate register use. CAPM fundamentals expect that broader view rather than a threats-only list.