A weekend water-main cutover plan must staff night-shift plumbers, traffic control, and an on-call engineer. What resource-planning outcome is the team producing?
Select an answer to reveal the explanation.
Short Explanation
Weekend cutovers are like pit stops: you need the right specialists in the right numbers for a tight window—night plumbers, traffic folks, on-call engineer—not a vague 'some people.'
Full Explanation
Determining number and type of resources means specifying the skill mixes and quantities required for the work package or window. A water-main cutover typically needs trade crews, traffic control, and engineering coverage together. Naming that package supports scheduling and procurement of scarce after-hours capacity. That is associate-level resource planning, not stakeholder surveying or product roadmapping.