A mobile crane subcontractor is mobilizing a 90-ton hydraulic crane onto a commercial hospital site where recent grading left soft backfill over an old utility trench. Who is responsible under OSHA 29 CFR 1926.1402 for ensuring ground conditions are firm, drained, and graded before crane assembly or operation?