Quiz 6 Question 4 of 20

A utility crew is excavating a 9-foot-deep trench in wet, granular Type C soil where groundwater seepage is visible along the lower walls. Under OSHA 29 CFR 1926 Subpart P, why must the safety technician reject the foreman's plan to bench the trench walls?

Select an answer to reveal the explanation.