Quiz 1 Question 4 of 20

During a scheduled process audit of a sterile pouch sealing line at a medical device manufacturer, an auditor notices a second automated heat-sealing machine in an adjacent bay that is not listed on the approved audit plan. What should the auditor do first?

Select an answer to reveal the explanation.