Quiz 13 Question 18 of 20

During bid tabulation for a county water utility's pipe supply Invitation for Bids, the buyer notices that a bidder wrote a unit price of 50 dollars per foot for 100 feet but calculated the extended total as 500 dollars instead of 5,000 dollars. Under standard public sealed-bidding rules, how should the buyer tabulate this item?

Select an answer to reveal the explanation.