Shortly after sealed bids are opened for a city's water-treatment chemical contract, the apparent low bidder notifies the buyer in writing that it transposed two digits in its unit price, submitting 12 dollars per gallon instead of 21 dollars per gallon, and attaches its original estimating worksheet. How should the buyer address this request before award?
Select an answer to reveal the explanation.
Short Explanation
An obvious typo is not a windfall for taxpayers; it is a recipe for a broken contract if ignored. You must verify the clear clerical error from objective worksheets and permit bid withdrawal without penalty, avoiding the trap of letting a bidder adjust its price upward after seeing competitors' numbers.
Full Explanation
Public procurement rules distinguish between errors in judgment, which remain the bidder's risk, and verifiable clerical or mathematical mistakes that would make enforcement unconscionable. When you verify the clear clerical error from objective worksheets and permit bid withdrawal without penalty, you protect both fair competition and contract viability by confirming the mistake from contemporaneous evidence and awarding to the next lowest responsive, responsible bidder. Choosing to allow the bidder to revise its price upward to match the second-low bid undermines sealed-bid integrity because post-opening price adjustments create opportunities for bid manipulation. Deciding to hold the bidder to the erroneous price regardless of the supporting worksheet risks contractor default, litigation, or degraded chemical supply once the vendor absorbs unsustainable losses. Choosing to cancel the entire solicitation immediately and re-advertise to all suppliers unnecessarily delays critical water-treatment supplies and exposes all competitors' prices without cause. Note that some jurisdictions require written determination by the chief procurement officer before releasing a bid bond. For an operational check, review the time-stamped estimating worksheets against the bid tabulation and document the withdrawal decision in the procurement file.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.