A municipal parks department plans to solicit bids for a new community aquatic center involving multiple electrical, plumbing, and concrete subcontractors. To protect the city against contractor default and unpaid subcontractor claims, which risk management instruments should the solicitation require from the awarded contractor?
Select an answer to reveal the explanation.
Short Explanation
A bid bond gets the contractor to the starting line, but it will not finish the race or pay the crew if things go south. You need performance and payment bonds to protect both project completion and subcontractor payments. The trap is confusing pre-award bid security with post-award protection.
Full Explanation
Public construction projects face both non-completion risk and non-payment claims from lower-tier trades, which is why the solicitation should require Performance and payment bonds guaranteeing project completion and subcontractor payment. A performance bond obligates a surety to step in or fund completion if the prime contractor defaults, while a payment bond ensures subcontractors and material suppliers are paid because public property generally cannot be encumbered by mechanics liens. Relying on A bid bond held by the city until the council approves the contract award misapplies bid security, which guarantees only that the winning bidder will sign the contract and furnish required post-award bonds. Requiring A certificate of commercial general liability insurance naming the city as additional insured addresses third-party injury and property damage rather than contractual default or unpaid labor and materials. Accepting A bid bond equal to ten percent of the bid, released at contract signing leaves the city exposed after award because bid security does not protect completion or subcontractors once released. As an exam caveat, statutory dollar thresholds for mandatory bonding vary by jurisdiction and public-works type. Operationally, verify the surety's licensing and bond amounts against the executed contract sum before issuing a notice to proceed.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.