Midway through a school district's high school HVAC replacement contract, unforeseen structural beam interference requires rerouting main ductwork. The contractor submits a 48,000-dollar change-order proposal with no labor-hour or material breakdown. What should the contract administrator do before executing the modification?
Select an answer to reveal the explanation.
Short Explanation
Once a contractor is on site, competitive pressure disappears, so change orders are a place where budgets can quietly bleed out. Protect your budget by requiring an itemized proposal and checking its costs against your own independent estimate before approving the modification.
Full Explanation
Post-award contract modifications occur in a noncompetitive environment, making cost and price analysis essential to protecting public funds. Before executing the modification, require an itemized breakdown and verify costs against an independent estimate: compare proposed labor hours, trade rates, equipment, and overhead markups with the base contract and an engineer’s estimate, then negotiate a fair bilateral change order. Approving the 48,000-dollar lump sum after the project engineer confirms the rerouting is necessary confuses scope need with price reasonableness and abdicates oversight, inviting inflated change-order pricing. Paying the lump-sum proposal through a separate purchase order and reconciling it at final closeout splits the contract obligation and skips change-order cost review, violating internal controls and distorting project spending. Re-bidding the entire HVAC replacement project to test current market labor rates is impractical and wasteful for a localized, in-scope field adjustment under an active construction contract. One caveat: if urgent schedule risk prevents immediate price agreement, the contract’s changes clause may allow a written directive to proceed while pricing is finalized under a not-to-exceed limit. As a practical check, obtain the district engineer’s independent estimate and verify any overhead-and-profit cap before signing the modification.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.