Quiz 5 Question 14 of 20

A county's three-year elevator maintenance contract expires in three weeks, and the replacement Request for Proposals is delayed by technical revisions. Facilities staff ask the incumbent contractor to keep servicing the elevators and promise to pay invoices once the new contract is signed. What should the contract administrator do?

Select an answer to reveal the explanation.