Midway through a municipal water-pump station upgrade, the contractor submits a written notice claiming extra excavation costs because the city-furnished engineering drawings showed an underground utility line in the wrong location. How should the contract administrator handle this claim?
Select an answer to reveal the explanation.
Short Explanation
When agency-furnished drawings miss an underground utility, telling the contractor to eat the cost is like giving someone a faulty map and blaming them for the detour. You need to verify the discrepancy with your technical team and document any justified adjustment in writing. The trap is either rejecting a valid claim out of hand or giving verbal approval that creates unauthorized financial exposure.
Full Explanation
When agency-supplied technical drawings contain inaccuracies that increase the contractor's work, the administrator must Verify the drawing discrepancy with the project engineer and execute a written modification if justified. Under public contracting principles, an agency generally warrants the adequacy of its own design specifications, so verified discrepancies require an equitable adjustment processed through formal contract channels. You should not Reject the claim because the contractor was required to verify site conditions before bidding, as doing so ignores agency-caused specification errors and invites formal disputes or litigation. Likewise, you must not Verbally authorize the contractor to proceed with the extra excavation and reconcile the final cost at project closeout, because verbal directives create unauthorized commitments and lose cost control. Choosing to Terminate the contract for default because the contractor stopped excavation to submit a cost claim is improper when the contractor is following contractual notice procedures for an agency-caused issue. As a caveat, verify whether the contract includes a differing-site-conditions or notice-deadline clause governing claim timing. Operationally, require itemized labor, equipment, and schedule documentation from the contractor before negotiating the bilateral modification.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.