Three months into a county's prevailing-wage public-works building contract, a union representative alleges that a plumbing subcontractor is paying apprentice helpers below the required journey-level rate without an approved apprenticeship program. Which contract administration action should the buyer take?
Select an answer to reveal the explanation.
Short Explanation
You have an ongoing duty to verify prevailing-wage compliance, not rely on a verbal promise or leave the allegation for the subcontractor to handle. Audit the certified payrolls and apprenticeship registration records before deciding whether further action is warranted.
Full Explanation
Under a prevailing-wage public-works contract, the county has an ongoing oversight duty. When underpayment is alleged, auditing certified payroll submissions and verifying apprenticeship registration records gives you objective evidence of worker classification and pay. Cross-check weekly payrolls against approved apprenticeship program certificates and daily site sign-in logs. Referring the union representative directly to the subcontractor and closing the inquiry abdicates the county’s statutory and contractual enforcement duty. Accepting the prime contractor’s verbal assurance does not create an auditable compliance record or protect underpaid workers. Terminating the prime contract for default and demanding repayment of all wages based on the union's allegation skips fact-finding and cure-notice procedures and may expose the county to wrongful-termination claims. A caveat: the prime contractor remains legally responsible for its subcontractors’ wage compliance, so any formal corrective notice or payment withholding must be directed through the prime. As a practical check, compare certified payroll hours with inspector daily field reports, then confirm that any underpayment identified has been corrected and restitution verified.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.