Quiz 4 Question 20 of 20

Midway through a state university's classroom-wing HVAC upgrade, the contractor submits a written claim for additional labor costs after encountering an unexpected ductwork routing conflict and threatens to pull its crew off the site until payment is approved. Which contract administration action should the buyer take?

Select an answer to reveal the explanation.

Motivation