Water-treatment operators are scheduled for SCADA-awareness training. Several lack the listed computer-skills prerequisite. What should the instructor do before delivery?
Select an answer to reveal the explanation.
Short Explanation
A prerequisite is a gate, not a wish. If operators barely use a keyboard, the SCADA class will stall on the first demo. Check actual skill against the listed bar before delivery, then decide how to proceed.
Full Explanation
Version 2.0 asks instructors to review learner backgrounds and compare current skill with course prerequisites before the event. Assignment to the roster is not evidence of readiness. Removing a required prerequisite or replacing the SCADA course with an unrelated IT fundamentals curriculum would compromise original design. The instructor assesses the gap first so logistics and any lawful customization can still serve the published objectives.