Quiz 2 Question 3 of 20

A firmware team at a consumer home-robot company is three days into a two-week Sprint when a supplier reports a PCB revision won't arrive until after the Sprint's original end date. The Scrum Master is asked to extend the current Sprint by a week to accommodate the delay instead of ending it on schedule. According to the Scrum Guide, what should happen to the Sprint's length?

Select an answer to reveal the explanation.