Metrics shown at Inspect and Adapt for the elections ART are only hours billed and story points completed. What should the Scrum Master / Team Coach push the ART to review?
Select an answer to reveal the explanation.
Short Explanation
Hours and story points are the odometer, not whether voters got a working ballot experience. Inspect and Adapt needs outcome and flow measures—results, flow time, predictability. Busy charts do not prove the elections ART improved.
Full Explanation
The quantitative and qualitative measurement portion of Inspect and Adapt is meant to inspect whether the ART delivered outcomes and how work flowed, not to celebrate effort theater. Hours billed, raw story points, utilization, and overtime are vanity or load signals that can look green while voter-facing flow time and predictability stay poor. The Scrum Master / Team Coach coaches the elections ART toward measures that inform problem-solving. Without those measures, the retrospective has nothing real to inspect.