Inspect and Adapt for the housing ART is only a System Demo, with no measurement review or problem-solving. What should the Scrum Master / Team Coach name as the full event?
Select an answer to reveal the explanation.
Short Explanation
A housing I&A that is only a System Demo is a ribbon-cutting with no inspection of the building. The event has three parts: demo, measures, and problem-solving. Skip two and the ART does not actually adapt.
Full Explanation
Inspect and Adapt has three parts: the PI System Demo, quantitative and qualitative measurement, and a retrospective that includes a problem-solving workshop. A demo plus a speech, metrics alone, or a team retro in place of the ART event are incomplete. The Scrum Master / Team Coach names all three so the housing ART inspects both the increment and the system of work. Improvement backlog items come from that full event, not from applause at the demo.