On the 911 CAD/RMS integration ART, nobody can say who prioritizes the Program Backlog. Who holds that content authority?
Select an answer to reveal the explanation.
Short Explanation
The Program Backlog is the ART's what-next list for 911 CAD/RMS. Product Management owns that list. The RTE keeps the event running; the architect guides the how—not the priority of every feature.
Full Explanation
In SAFe, Product Management has content authority for the ART: vision, roadmap, and prioritization of the Program Backlog. The RTE facilitates events and flow; System Architect/Engineering guides technical direction and enablers; Scrum Master/Team Coaches serve teams. Assigning backlog priority to the RTE or architect confuses servant leadership and technical guidance with content authority.