Day 2 of court case-management ART PI Planning starts without reconciling Day 1 dependencies or management-review adjustments. What facilitation step is missing?
Select an answer to reveal the explanation.
Short Explanation
Day 2 is not a new island. Court teams have to pick up yesterday's collisions and the management-review notes before they lock the plan. Facilitate that reconciliation first or Day 2 just reprints Day 1's mess.
Full Explanation
PI Planning is a two-day facilitation arc: Day 2 begins by reconciling Day 1 dependencies and management-review adjustments, then teams rework plans. Starting over, freezing Day 1, or deferring reconciliation to a later ART Sync breaks continuity. The RTE keeps the case-management ART's program board and adjustments visible across both days.