Three Scrum Teams will demo a transit real-time-arrivals product. Each team scheduled its own isolated demo with a different stakeholder group. What should the Product Owner coordinate instead?
Select an answer to reveal the explanation.
Short Explanation
Three private demos of one transit app is three people describing different pieces of the same bus. Riders experience one product. Get stakeholders in one Review looking at the integrated Increment.
Full Explanation
Stakeholders need to inspect the integrated product Increment to give feedback that can adapt a single Product Backlog. Isolated component demos hide integration gaps and produce conflicting stakeholder signals. The Product Owner should coordinate a Review of the whole arrivals product; team-level walkthroughs may support preparation but cannot replace that inspection. Status meetings and slide tours are not a Sprint Review.