Quiz 7 Question 10 of 20

A food-processing facility plans to install a new industrial refrigeration system that will hold a regulated toxic substance in a single interconnected process above the federal threshold quantity established under Clean Air Act Section 112(r). During pre-installation planning, which federal regulatory program requirement must the EHS manager address before bringing the regulated substance on site?

Select an answer to reveal the explanation.