A town wants predictive RF design started immediately, but departments still disagree on VoWLAN, guest isolation, and coverage in temporary trailers. What should gate design work?
Select an answer to reveal the explanation.
Short Explanation
Don’t draw the blueprints while the family is still arguing about how many bedrooms. Get stakeholders to sign the requirements—voice, guest rules, trailer coverage—then design. Designing first and negotiating later is how you buy the wrong house twice.
Full Explanation
Requirements approval is a design gate: business and technical specifications (applications, SLAs, security, coverage areas, constraints) must be agreed before predictive/measured design consumes budget. Starting from vendor defaults or installer improvisation embeds unverified assumptions. Over-provisioning AP count without requirements still fails acceptance when use cases were never defined.