The DR plan describes vendor phone numbers but never names who may declare a disaster and activate the alternate site. What planning element is missing?
Select an answer to reveal the explanation.
Short Explanation
If nobody is allowed to yell 'go,' the spare site stays dark while people argue. Activation authority and criteria are the starter pistol. Put names and triggers in the plan before the outage starts.
Full Explanation
Disaster recovery plans must specify activation criteria and the roles authorized to declare a disaster and invoke alternate sites. Without that clarity, delays and conflicting decisions occur under stress. Clear activation governance accelerates coordinated recovery.