A grant-funded literacy program ends on schedule, but remaining funds reconciliation and the final grant report are still open. What closure responsibility remains?
Select an answer to reveal the explanation.
Short Explanation
The tutoring sessions can stop and the project still is not truly done. Someone still has to reconcile the grant money and file the final report—that is administrative closure, not optional homework.
Full Explanation
Administrative closure completes contractual, financial, and reporting obligations even after primary deliverables are finished. Grant-funded work commonly requires final reports and fund reconciliation before the project is fully closed. Leaving those items open keeps the endeavor administratively incomplete. CAPM closure topics include that administrative and transition completeness, not only stopping day-to-day delivery work.