During demolition of a 1970s school boiler room, a laborer begins tearing out crumbling white fibrous pipe insulation that is not listed on the pre-job hazardous-materials survey. What should the supervisor do immediately?
Select an answer to reveal the explanation.
Short Explanation
In a 1970s building, crumbling white pipe wrap is presumed to contain asbestos until qualified testing proves otherwise. If you let the crew wet it down or sweep it up without a plan, you can contaminate the entire building and expose workers to irreversible lung fibers.
Full Explanation
Under 29 CFR 1926.1101, thermal system insulation in buildings constructed before 1981 is presumed asbestos-containing material, so the supervisor must "Stop demolition in the area, restrict access, and arrange qualified asbestos sampling". Isolating the zone prevents airborne fibers from spreading through HVAC chases or corridors while an accredited inspector determines whether regulated abatement is required. Choosing to "Have the laborer wet the insulation with a garden hose and bag it in clear trash bags" uses unapproved containment and uncertified workers, risking fiber release and improper disposal. Choosing to "Issue disposable filtering facepiece dust masks and finish clearing the boiler room" fails because standard dust masks do not provide compliant respiratory protection or engineering containment for asbestos. Choosing to "Sweep the fallen debris into a wheeled bin at the end of the shift to keep dust down" dry-sweeps presumed asbestos, which violently resuspends microscopic fibers into the breathing zone. As a caveat, even if the pre-job survey missed a hidden pipe chase, demolition must pause whenever suspect material appears. As an operational check, post warning barriers at all boiler-room doors and verify negative results or licensed abatement clearance before resuming work.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.