During an elevated concrete deck pour on a commercial building, a section of shoring buckles and partially collapses, knocking down wet formwork while several workers scramble clear. What should the site supervisor order immediately?
Select an answer to reveal the explanation.
Short Explanation
A shifting formwork deck is a trap waiting to drop a second time—your first job is getting everyone out and calling technical rescue. The trap is rushing back under unstable shoring or trying to balance the pour instead of securing the scene.
Full Explanation
After a partial formwork collapse, the supervisor must Evacuate the collapse zone, account for all crew members, call 911, and bar re-entry. Structural collapses often trigger secondary failures as wet concrete and damaged shoring continue shifting, so immediate evacuation, headcount verification, and trained emergency rescue response protect survivors and prevent additional casualties. Choosing to Send laborers under the tilted shoring to prop it up with spare lumber exposes workers to sudden crushing hazards beneath overloaded, failing supports. Continuing to Keep pumping concrete into the adjacent bay to balance the deck load adds massive weight and vibration to a compromised falsework system, risking a wider progressive collapse. Stopping to Ask the crane operator to lift the fallen formwork before calling EMS delays professional medical and rescue response and can shift tangled debris onto trapped workers. As a caveat, shut off the concrete pump and isolate energized utilities in the collapse area if it can be done safely from outside the hazard zone. Meet arriving emergency responders at the site gate with the crew roster and structural layout so rescue teams know the exact headcount and access points.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.