Quiz 14 Question 11 of 20

A general contractor's subcontract includes an indemnification clause stating that the electrical subcontractor assumes full responsibility for its own safety compliance, so the project superintendent stops checking the subcontractor's work areas. Why does this approach fail under safety program and risk management principles?