Quiz 8 Question 11 of 20

A utility crew is digging a 5.5-foot-deep trench in cohesive clay soil to repair a storm drain and plans to work inside for only fifteen minutes without shoring or sloping. Under OSHA 29 CFR 1926.652, what must the safety technician require?

Select an answer to reveal the explanation.