Quiz 5 Question 6 of 20

A project superintendent wants to strip shoring and formwork beneath an elevated concrete slab 72 hours after the pour to keep the schedule moving, even though cold weather slowed curing. What must happen before formwork is removed under 29 CFR 1926.703(e)(1)?

Select an answer to reveal the explanation.