Following an internal audit of a sterile-syringe packaging line, a quality engineer wants to track the daily proportion of rejected pouches across varying daily production lot sizes to confirm that corrective actions are holding. Which control chart is most appropriate for this data?
Select an answer to reveal the explanation.
Short Explanation
When your daily inspection count changes from shift to shift, you need a chart that measures the percentage of bad units rather than raw counts. A p-chart handles those shifting lot sizes cleanly, saving you from the trap of forcing a constant-sample chart onto variable daily output.
Full Explanation
Monitoring pass/fail attribute data when the total number of inspected units varies each day requires A p-chart to monitor the fraction of nonconforming pouches across varying lot sizes. Because the p-chart plots the proportion defective and adjusts control limits as subgroup sizes change, it accurately flags special-cause shifts in rejection rates. Choosing An X-bar and R chart to track average pouch weight and within-subgroup range applies a variables chart meant for continuous measurements rather than discrete pass/fail counts. Choosing A scatter diagram to plot daily production volume against total customer complaints evaluates correlation between two paired variables rather than time-ordered process stability. Choosing A c-chart, which requires a constant sample size of inspected pouches every day fails when daily production lot sizes fluctuate, because raw defect counts naturally rise and fall with volume. As a caveat, if the subgroup size varies dramatically from day to day, control limits will step up and down unless standardized limits are used. Operational check: confirm that each pouch is classified clearly as conforming or nonconforming and record both the reject count and total inspected lot size daily.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.