Quiz 13 Question 13 of 20

An audit program manager uses a risk-based schedule that audits high-risk sterile-processing lines quarterly while repeatedly deferring low-risk administrative support processes. After three years, a neglected administrative process causes widespread training-record errors. How should the audit program manager adjust the program governance?

Select an answer to reveal the explanation.