Quiz 11 Question 13 of 20

Midway through an on-site process audit of a specialty chemical plant, an auditor drafts a preliminary nonconformity after misreading a pressure gauge scale as bar instead of kilopascals. Upon reviewing the equipment specification sheet with the line engineer, the auditor realizes the reading was actually within specification. What should the auditor do?

Select an answer to reveal the explanation.

Motivation