On the morning of day two of a three-day multi-auditor quality system audit, one of the three auditors falls ill and cannot participate. How should the lead auditor respond?
Select an answer to reveal the explanation.
Short Explanation
Losing a teammate mid-audit is like losing a runner in a relay race—you adjust the handoffs and keep moving rather than walking off the track! Reassign the remaining work to qualified auditors and keep the auditee informed of any schedule shifts to maintain coverage. The trap is asking an auditee employee to fill in or silently dropping departments from the report.
Full Explanation
The lead auditor should reallocate tasks among qualified team members and update the auditee on schedule changes. This preserves audit coverage while ensuring that the auditors handling reassigned processes remain competent and independent. Promptly informing the auditee gives escorts and process owners time to adjust their availability and helps avoid disrupting operations. Canceling the remaining two days and rescheduling the entire assessment for next quarter wastes completed fieldwork when the remaining team can cover or reprioritize critical areas. Asking a supervisor from the auditee’s quality department to substitute compromises auditor independence because the auditee would be auditing itself. Omitting the ill auditor’s assigned departments from the final report without informing the auditee breaches fair presentation and misrepresents the audit scope. One caveat: if the remaining qualified staff cannot cover a specialized high-risk area within the available time, document the scope limitation in the report and consult the audit client. As a practical check, hold a brief team caucus before day two’s work resumes to rebalance sampling priorities and confirm the schedule with the auditee.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.