Six months ago, an audit at an automotive stamping supplier found that press operators skipped first-piece dimensional checks during die changeovers. In response, the supplier retrained all operators and revised the work instruction. During follow-up verification, what provides the strongest evidence that the corrective action is effective?
Select an answer to reveal the explanation.
Short Explanation
Training attendance sheets only prove people sat in a room; they never prove the fix actually worked on the shop floor. The trap is closing a corrective action as soon as the paperwork is signed or the class is taught. Look for sustained execution in real production records and a drop in repeat defects before you call it effective.
Full Explanation
Corrective action verification must confirm not only that planned actions were implemented, but also that they eliminated the root cause and prevented recurrence. The most compelling proof is Recent changeover logs and zero repeat defects across multiple production runs. Sustained operational records over time demonstrate that the new behavior took hold under normal production pressures and produced measurable quality improvement. Relying on Training sign-off sheets showing all operators attended the refresher only confirms that training occurred, not that operators apply the steps correctly at the press. Relying on A revised work instruction signed by the engineering manager last month proves document update completion rather than shop-floor compliance or defect reduction. Accepting A verbal confirmation from the shift lead that operators follow the rule is hearsay without objective corroboration. As a caveat, if no die changeovers occurred during the verification window, the corrective action should remain open until sufficient operating cycles provide a valid sample. As an operational check, sample changeover records across different shifts and presses rather than checking only the day shift.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.