Upon opening sealed bids for a school district roof-coating Invitation for Bids, the buyer sees that the apparent low bid is forty percent below both the independent cost estimate and the next lowest bid. What action should the buyer take before recommending award?
Select an answer to reveal the explanation.
Short Explanation
When a sealed bid comes in forty percent below both benchmarks, you’re right to pause: it may reflect a missing zero or an omitted line item. Request written verification from the bidder before recommending award, so you can confirm the bid without letting the bidder change its price. Rushing to award or allowing a price increase after opening can create serious problems.
Full Explanation
An anomalously low sealed bid may reflect a serious mathematical or clerical error that could lead to contractor default or post-award disputes. Before recommending award, request written verification from the bidder to check for a potential mistake. Seeking confirmation without disclosing competitors' prices or the internal estimate protects both the agency and the bidder: it confirms that the bid is firm or surfaces a documented mistake governed by withdrawal rules. Recommending immediate award to lock in the savings can mean accepting an obvious mistake, risking abandoned work, liens, or costly re-procurement. Rejecting the low bid as non-responsible because it falls far below the estimate and the next bid is also unjustified, because low pricing alone may reflect legitimate efficiencies or inventory advantages rather than lack of capability. Allowing the bidder to increase its price to match the second-lowest bid is impermissible; a post-opening upward price modification violates sealed-bidding integrity. As an exam caveat, if the bidder claims an error, apply your jurisdiction's strict standard for clear and convincing evidence of a non-judgmental mistake before allowing withdrawal. As a practical check, document the verification request, the bidder's written confirmation, and the comparison with the independent cost estimate in the procurement file.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.