Quiz 14 Question 3 of 20

While tabulating unit-price bids for a municipal sewer rehabilitation project, a buyer notices that the apparent low bidder priced early mobilization and excavation items far above market rates while pricing later pipe-lining items at one cent per foot. Which sourcing action should the buyer take?