A state university plans a complex, multi-phase renovation of an occupied science laboratory building and needs early contractor constructability advice during design along with a Guaranteed Maximum Price before major construction begins. Which project delivery method best fits these needs?
Select an answer to reveal the explanation.
Short Explanation
Renovating an occupied lab building is like remodeling a kitchen while dinner is still cooking—you need the builder at the table before demolition starts. The trap is defaulting to Design-Bid-Build, which keeps the contractor locked out until drawings are finished. Choosing Construction Manager at Risk gives you early constructability input and a price ceiling.
Full Explanation
Selecting the right construction delivery method during pre-solicitation planning aligns technical collaboration, schedule phasing, and cost risk with project complexity. Choosing to use Construction Manager at Risk with pre-construction services and a negotiated maximum price allows the university to select a qualified contractor during design to advise on occupied-building phasing, long-lead equipment, and constructability before locking in a Guaranteed Maximum Price. Choosing Traditional Design-Bid-Build using sequential design completion and a single low-bid construction award prevents contractor input during design and increases change-order risk in complex renovations. Choosing A job-order contract priced from a unit price book lacks the preconstruction advice and guaranteed maximum price structure needed for a major occupied-lab renovation. Choosing Multiple-award indefinite-delivery supply contracting for direct university equipment purchases addresses commodity buying rather than integrated construction management. As an exam caveat, confirm statutory authority before using alternative delivery methods, as some jurisdictions restrict CMAR to specific thresholds or approvals. As an operational check, define clear pre-construction deliverables and open-book cost-validation rules before finalizing the solicitation.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.