Quiz 8 Question 17 of 20

A county public works department is preparing a sealed-bid solicitation for stormwater culvert replacements, and the project engineer asks to skip internal cost estimating and simply rely on incoming contractor bids to set fair market pricing. What should the buyer do during pre-solicitation planning?

Select an answer to reveal the explanation.