A county public works department is preparing a sealed-bid solicitation for stormwater culvert replacements, and the project engineer asks to skip internal cost estimating and simply rely on incoming contractor bids to set fair market pricing. What should the buyer do during pre-solicitation planning?
Select an answer to reveal the explanation.
Short Explanation
Sending out a solicitation without a price benchmark is like shopping for a car without ever checking market values. Your trap is assuming incoming bids automatically reflect fair pricing, when thin competition or inflated estimates can easily skew the pool. Always anchor your planning with an independent estimate before opening competition.
Full Explanation
Choosing to "Prepare an independent cost estimate before issuing the solicitation" gives the agency an objective baseline for budget sufficiency, solicitation method selection, and post-opening price reasonableness analysis. Without an independent estimate, buyers cannot easily tell whether a low bid is a bargain or whether all bids are inflated above current market rates. Relying on "Solicit non-binding price quotes from local contractors to set the budget" risks anchoring the agency's budget to vendor-supplied figures and can create an unfair informational advantage if those firms later bid. Choosing to "Use the prior decade's awarded contract price without adjusting for scope" ignores inflation, material market shifts, and site-specific engineering differences that invalidate outdated pricing. Planning to "Publish the solicitation with a budget cap based on the last three low bids from similar culvert projects" substitutes recalled totals for analysis without quantity takeoffs, scope adjustments, or current market data, so it is still not an independent cost estimate prepared before issuance. Caveat: cost estimates should be updated whenever technical specifications change before advertisement. As an operational check, document the estimator's sources—such as recent unit-price tabs, public indices, or engineering takeoffs—in the solicitation file before releasing the bid.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.