Quiz 4 Question 15 of 20

Halfway through a municipal recreation center construction contract, the general contractor reports that the specified commercial air-handling units face a 20-week factory backorder and asks to substitute an alternate manufacturer's model to maintain the schedule. What should the contract administrator do before approving the substitution?

Select an answer to reveal the explanation.