Halfway through a municipal recreation center construction contract, the general contractor reports that the specified commercial air-handling units face a 20-week factory backorder and asks to substitute an alternate manufacturer's model to maintain the schedule. What should the contract administrator do before approving the substitution?
Select an answer to reveal the explanation.
Short Explanation
When a backorder threatens your construction schedule, a quick verbal nod feels tempting, but informal swaps can quietly undermine performance and warranty protections. Before any alternate equipment goes into the building, you need formal technical verification, a price-difference check, and a signed contract change. The trap is treating schedule pressure as an excuse to skip written documentation or assuming substitutions are either always banned or free to approve on the spot.
Full Explanation
Post-award substitutions require formal contract control so the agency preserves specification value. The right step is to: Require documented technical equivalency review, verify any cost savings, and execute a written contract modification before installation. This mechanism ensures engineers verify capacity and compatibility while procurement captures any price credit in a binding bilateral change. It is a mistake to: Allow the contractor to install the alternate unit immediately if the project superintendent confirms it fits the mechanical room. Doing so bypasses technical review and creates an unauthorized commitment that risks inferior performance. Likewise, do not: Reject post-award substitution requests as a matter of policy and direct the contractor to wait for the specified units. Rigid refusal ignores real supply-chain delays that a structured equivalency review can safely resolve. Nor should you: Permit the substitution without a contract amendment as long as the contractor absorbs any price difference and keeps the original completion date. Skipping a formal amendment leaves the contract mismatched with installed equipment and forfeits savings if the alternate costs less. As a caveat, verify that the contract permits post-award substitutions without undermining fair competition. For an operational check, confirm the signed modification, technical sign-off, and updated submittal log are filed before inspection.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.