Quiz 5 Question 4 of 20

Two weeks into a Sprint, the app team realizes a selected Product Backlog item is more complex than expected. They talk with the Product Owner and agree to trade it for a different item that still supports the agreed Sprint Goal. What does this exchange demonstrate about the relationship between the Sprint Goal and Sprint Backlog scope?

Select an answer to reveal the explanation.