Quiz 1 Question 17 of 20

A hardware certification lab tells the Developers a required safety test can only run once every two weeks due to lab scheduling, which conflicts with the company's weekly Sprint cadence. This is a constraint outside the Scrum Team's control. Whose accountability is it to raise this as an organizational impediment if it is blocking progress?

Select an answer to reveal the explanation.