The paratransit-scheduling team wants to keep Scrum events and add a Kanban board. How should the SM/TC treat that mix?
Select an answer to reveal the explanation.
Short Explanation
A paratransit team can keep Sprint Goals and still put work on a board. That is Scrum using a Kanban system, not a secret third religion. Do not make them burn the events or invent a new method name.
Full Explanation
SAFe Scrum teams may visualize and limit WIP with a Kanban system while still running Scrum events and iteration goals. The official team-process choice remains SAFe Scrum versus SAFe Team Kanban, not a third branded hybrid to memorize. Forbidding the board, auto-dropping events, or asking an SPC to christen a new method all over-formalize a practical mix. Coach the team-process choice; allow the board as a flow tool.