Demo feedback on the open-data team is never put on the backlog. What should the Scrum Master / Team Coach close?
Select an answer to reveal the explanation.
Short Explanation
Cheering an open-data demo and then losing the comments is applause with no encore list. If feedback never hits the backlog, the review had no outcome. Write it down where the next plan can see it.
Full Explanation
Iteration Review produces an inspected increment and new information. That information only becomes an outcome when it enters the backlog or plan. Slide archives, director email, and waiting until PI Planning all drop the loop. The Scrum Master / Team Coach closes the loop with the Product Owner so open-data stakeholders can see their feedback change future work.